Maui B drilling end of project report

Login to download

Maui B drilling project was completed in 550 days commencing on 10/10/93 and finishing on 29/4/94. Ten oil and gas wells including two horizontal wells were drilled, nine completions installed and one workover done in a project that expanded from its original 8 well scope due to the discovery of oil in MB-(V)3 deepening. This report summarises the failures and successes of each well and each drilling phase, with a view to assisting future operations. Extensive reference lists are included.

Report ID pr1567
Class Petroleum
Type Well Report - Completion
Permit 381012
Operator SHELL BP & TODD OIL SERVICES LTD
Commodity Petroleum
Region Taranaki Basin
Start Date 01 January 1994
End Date 31 December 1994