CR3680
Hawkdun Project - Technical report MEP55175
This report documents all work completed by PR Exploration Pty Ltd at the Hawkdun Project, Otago, for the 36 months period to 7th November 2016. Work completed on the permit...Permit55175Start Date07 November 2013FormatsPDF ZIPData TypeReport -
CR3669
CPP 54935 - Waitaki Work Program Report 2016
This report outlines the work completed with regards to CPP 54935 located within the Waitaki Valley area of Otago by Bathurst Coal Ltd during the reporting period December 2013...Permit54935Start Date17 December 2013FormatsPDF ZIPData TypeReport -
CR3664
CEP 40591 - Whareatea West Work Program Report 2016
This report outlines the work completed within CEP 40591, the Whareatea West project during the period December 2013 to December 2015. Completed work includes infill drilling,...Permit40591Start Date19 December 2015FormatsPDF ZIPData TypeReport -
CR3648
CPP 56566 Waiau Basin Surrender Report 2015
The Waiau Basin Permit (PP56566) was applied for to prospect for any continuation of coal bearing horizons identified by Oreti Resources in EP54495 Loudon Hill to the east. The...Permit56566Start Date30 January 2015FormatsPDF ZIPData TypeReport -
CR3646
Coal Exploration Permit 53158 Malvern Hills - Interim Report 2015
This interim report outlines the work carried out by L&M Coal Whitecliffs Limited on Coal Exploration Permit 53158, Malvern Hills, Canterbury region during the period July...Permit53158Start Date09 July 2012FormatsPDF ZIPData TypeReport -
CR3645
CEP 53250 Technical Report 2015
This report documents the work completed by Solid Energy on coal exploration permit 53250, Maramarua Coalfield during the first 36 months of the license period up until June...Permit53250Start Date15 June 2012FormatsPDF ZIPData TypeReport -
CR3644
Surrender Report for CEP 54495, Loudon Hill Block 2015
This Coal Surrender Report outlines the work carried out on CEP 54495, Loudon Hill, from May 2013 to June 2015. During the last two years Oreti Resources has completed a...Permit54495Start Date07 May 2013FormatsPDF ZIPData TypeReport -
CR3643
Relinquishment Report for CPP 53687 - Victoria Range 2015
This surrender report outlines the motivations behind the relinquishment of MPP 53687, Victoria Range Coal Project, June 2015 and the work completed since the last reporting...Permit53687Start Date18 October 2013FormatsPDF ZIPData TypeReport -
CR3642
Relinquishment Report for CPP 53690 - Mt Lindon 2015
This surrender report outlines the motivations behind the relinquishment of MPP 53690, Mt Linton Coal Project, June 2015 and the work completed since the last reporting period....Permit53690Start Date27 October 2013FormatsPDF ZIPData TypeReport -
CR3641
Relinquishment Report for CPP 53993 - Piko Piko 2015
This surrender report outlines the motivations behind the relinquishment of MPP 53993, Piko Piko Coal Project, June 2015 and the work completed since the last reporting period....Permit53993Start Date13 December 2013FormatsPDF ZIPData TypeReport -
CR3640
CEP 53478 Work Programme Report
This work programme report outlines the work carried out by Roa Mining on CEP 53478 within the Greymouth coalfield for the period November 2012 to July 2015. Works completed...Permit53478Start Date11 July 2012FormatsPDF ZIPData TypeReport -
CR3638
Surrender Report on PP 55463 Southland July 2015
Surrender Report states the reasons for relinquishment of the permit and also describes the work completed until Aug 2014 since its grant Aug 2012. This PP 54463 permit was held...Permit54463Start Date17 August 2012FormatsPDF ZIPData TypeReport -
CR3637
EP 53535 Garvey Creek Coalfield Technical Report 2015
This report outlines the work completed by Francis Mining Co within CEP 53535 for the reporting period July 2012 to July 2015. Completed works include a review of all available...Permit53535Start Date06 July 2012FormatsPDF ZIPData TypeReport -
CR3633
CEP 54846 24 Month Compliance Report
This report by Bathurst Resources summarises the work completed on CEP 54846, the Albury Project during the period March 2013 to March 2015. Completed work includes the...Permit54846Start Date05 March 2013FormatsPDF ZIPData TypeReport -
CR3632
CEP 51212 Moody Creek Partial Surrender Report
This partial relinquishment report summarises the work undertaken by Buller Coal June 2009 to March 2015 on the surrendered portion of CEP 51212. Preliminary mapping, drilling...Permit51212Start Date12 June 2009FormatsPDF ZIPData TypeReport -
CR3578
PP 53993 Piko Piko annual technical report - 2013
Report embodies the exploration work carried out by PR Exploration Pty Ltd at PP53993, located on the eastern extremity of the Waiau Basin, overlapping with the West Longwoods...Permit53993Start Date20 December 2012FormatsPDF ZIPData TypeReport -
CR3573
MP 41269 Echo exploration data - 2011
Report includes the exploration work completed by Francis Mining Co Limited at Echo Mine area, West Coast during the period between March 2010 and March 2011. Work completed...Permit41269Start Date28 March 2010FormatsPDF ZIPData TypeReport -
CR3572
MP 41269 Echo exploration data - 2010
Report includes the exploration drilling and geological work undertaken by Francis Mining Co Limited at Echo Mine, West Coast during the period between March 2009 and March...Permit41269Start Date28 March 2019FormatsPDF ZIPData TypeReport -
CR3569
PP 53690 Mt Lindon annual techncial report - 2013
Report describes the exploration work carried by PR Exploration Pty Ltd on PP53690 during Oct 2012 and Oct 2013 at Mt Linton located on the eastern extremity of the Waiau Basin,...Permit53690Start Date28 October 2012FormatsPDF ZIPData TypeReport -
CR3559
PP 54463 Hedgehope Annual Technical Report - 2013
This report outlines the exploration work completed by Oreti Resources Limited between August 2012 and August 2013 for the prospecting permit (PP) 54463 in Southland. Work has...Permit54463Start Date17 August 2012FormatsPDF ZIPData TypeReport