Report

Mangahewa-28 Stimulation and Testing Activities Report

Login to download

This report summarises the stimulation and testing activities for Mangahewa-28 carried out between 15.07.2019 and 04.09.2019, and is an addendum to the well completion report (PR5809). 11 intervals were perforated and fracced, utilising a stack and frac strategy. All but one interval was found, via PLT testing, to be contributing gas. A total well production rate of 18MMscf/d was achieved.

Report ID pr5797
Class Petroleum
Type Well Report - Test
Permit 38150
Operator Todd Energy Ltd.
Commodity Petroleum
Region Taranaki Basin
Start Date 15 July 2019
End Date 04 September 2019
Report extents in GeoJSON
Author Michelle Cook & Sarah Balsom
Data Format
  • PDF