Report

Kaimiro-1 ST2 Well Testing Report (Addendum to PR5759)

Login to download

This report discusses well testing activities carried out on the Kaimiro-1 ST2 well in PMP 38148, onshore Taranaki Basin. No stimulations were preformed. The upper 19m of pay is behind the 7 casing and cement, this section has been perforate. The remainder of the reservoir section was left open to flow through a slotted liner. Testing throughout March 2019 showed production of up to 6 MMscf/d of gas with ~150 bopd condensate and ~20 bwpd produced water from the Mangahewa formation. The well is now producing gas condensate for export.

Report ID pr5817
Class Petroleum
Type Well Report - Test
Permit 38148
Operator Greymouth Petroleum Central Limited
Commodity Petroleum
Region Taranaki Basin
Start Date 01 March 2019
End Date 31 March 2019
Report extents in GeoJSON
Author Kumaravel A