MR5599
Annual Technical Report: MP55549 - Chatham Rise Project
This report from Chatham Rock Phosphate is an update mine schedule planning and resource optimisation work for MMP55549 during the year up to December 2018. Environmental data...Permit55549Start Date06 December 2017FormatsPDF ZIPData TypeReport -
MR5315
MMP 55549 -Chatham Rise Phosphate Annual Technical Report 2016
This Annual Technical Report describes the work completed with regards to MMP 55549 - The Chatham Rise Phosphate project. Completed work includes a study into the effectiveness...Permit55549Start Date12 February 2016FormatsPDF ZIPData TypeReport -
MR5194
Technical report for MEP 54271 March 2015-offshore Waikato
This Technical Report outlines the work carried out by Trans-Tasman Resources Limited within MEP 54271, titano-magnetite prospect, inshore offshore Waikato during 2014. Work...Permit54271Start Date01 January 2014FormatsPDF ZIPData TypeReport -
MR5193
Technical report for MEP 54068 March 2015-inshore Taranaki Bight
This Technical Report outlines the work carried out by Trans-Tasman Resources Limited within MEP 54068, titano-magnetite prospect, inshore Taranaki Bight during 2014. Work...Permit54068Start Date01 January 2014FormatsPDF ZIPData TypeReport -
MR5192
Technical report for MEP 50753 March 2015-offshore Taranaki Bight
This Technical Report outlines the work carried out by Trans-Tasman Resources Limited within MEP 50753, iron sand prospect, offshore Taranaki during 2014. Work completed during...Permit50753Start Date01 January 2014FormatsPDF ZIPData TypeReport -
MR5073
CSL 50270 Chatham Rise phosphate annual technical report - 2014
This report by Kenex Ltd details the work completed by Chatham Rock Phosphate Limited (CRP) between February 2012 and February 2014 for the Continental Shelf Licence (CSL) 50270...Permit50270Start Date25 February 2012FormatsPDF ZIPData TypeReport -
MR4994
EP 54305 Springs Junction Technical Report - 2013
This report outlines the exploration work completed by R K Murdoch Pty Ltd between September 2012 and July 2013 for the exploration permit (EP) 54305 on the West Coast. Work...Permit54305Start Date19 September 2012FormatsPDF ZIPData TypeReport -
MR4923
EP40542 Blackwater Final Report 2013
Report outlines all exploration activity completed within EP40542 by Oceana Gold between Feb 2012 and Nov 2012. Work completed includes a completion of 33 drill holes, which...Permit40542Start Date01 February 2012FormatsPDF ZIPData TypeReport -
MR4899
EP40795 Windsor Final Technical Report
Report describes the pit plans feasibility studies for all the raw material deposits completed by Golder Associates on behalf of Holcim (New Zealand) Ltd at EP40795 Windsor...Permit40795Start Date24 May 2009FormatsPDF ZIPData TypeReport -
MR4736
EP 40525 Annual Summary Activity Report on Pebbly Hills, Southland for the year ending 3 May 2011
This report summarises and discusses the results of investigations by Silicon Metal Industries (NZ) Ltd (SMINZ) into the potential for economically exploitable silica within...Permit40525Start Date03 May 2010FormatsPDF ZIPData TypeReport -
MR4655
Technical Report on Waipipi to 11 January 2010
This report contains results of exploration completed by Sericho Developments Limited on EP40695 from January 2005 to January 2010. Work completed includes mapping, geochemical...Permit40695Start Date11 January 2010FormatsPDF ZIPData TypeReport -
MR4399
Technical Report E40525 Pebbly Hills. 3rd Sept 2006 to 3rd May 2008
This report covers work done during the extension of duration period including an evaluation of the resource and initial feasibility planning.Permit40525Start Date03 September 2006FormatsPDF ZIPData TypeReport